Home Construction Diaries
Saturday, 8 December 2012
Preparation for concrete flooring of basement
The most costly item in construction work is Sariya (Deformed Steel Bars). There are many companies preparing sariya like model steel, nazir sons, ittefaq steel etc. We got Nazir Sons steel 1 ton of 3/8 inch and 1 ton of 4/8 inch for about 73 Rs per Kg. Steel mesh was formed for concrete flooring and for concrete wall.
Margala Bajri Truck arrived
Bajir truck arrived at about 5.30 in the morning. It was a chilly morning. Our contractor had arranged it and it came all the way from taxila at rate of 59 per sq foot. It was a big Hino truck we were expecting about 600 sq feet but when we measured it was 925 sq feet. These guys only take cash payments. So be ready with extra bucks !!
Margala bajri is considered best. Sargodha bajri is between 50-55 per sq feet, however its quality is quite lower.
Margala bajri is considered best. Sargodha bajri is between 50-55 per sq feet, however its quality is quite lower.
Filling of Basement Floor
Next day, basement floor was filled with rhorhi and afterwards covered with mixture of sand and cement. We got trolley of broken bricks(rhorha) for about 12k which had about 450 sq feet stuff. afterwards this rhorha was converted in rhorhi. A trolley of sand costed us 5.3k.
You can see we have started excavation of remaining foundation walls as well.
Termite Proofing for Basement
Termite proofing was done for basement wall and floor. Its more effective on bare soil as compared to when applied on floor full of rhorhi. Well it took about 1 gallon of chemical in a drum of water of about 100 liters. There are many brands available from many companies like biflex, fmc, 4brothers, Ali Akbar, Stadec etc.
Sunday, 2 December 2012
Excavation for basement
These people charge you heavily if the excavated soil is left at the site but if they take it with them then huge discounts are available. Problem is that nearly all socities have banned transportation of soil from within their premises to outside.
Manual digging can be costly and time consuming. Excavator took nearly 2 hrs for digging 450 sq foot. Really a life saver !!
Excavation team charged us 15k which included smoothning of floor and walls soil.Working space for excavator is very important. Overhead wapda lines can get very close to its elbow at certain angles . Make sure you have ample space.
Saturday, 27 October 2012
Construction of store room
After two days, construction work for the store started. It was my first experience in the field of civil works so was very much excited. I got in contact with a contractor through my brick supplier. At first he was reluctant to work with pre-casted concrete roof as he preferred TI girders roof with tile bricks but then agreed. Three labourers and one mason (raj) came with contractor to start the work. Room is 10 feet in depth,15 feet in width with 9 inch walls included.
Carefully all concrete girders were placed and afterwards slabs were placed one by one. Special care should be taken while placing girders, if they hit the wall they can easily damage the wall specially one made from gara.
After all the slabs were placed, cement (mortar) was applied in the spaces between the slabs. Plastic sheet was placed above it and then Gara+Turi mixture was applied all over it. Roof's surface level was adjusted for drainage and plastic pipe was fitted to complete the work.
COST ANALYSIS Rs.
1) 4000 Bricks 29000
2) Izhar Concrete roof 12000
3) Iron Door 4500
4) Iron Window 1200
5) Labour cost 10000
6) Cement 1 Bag+2 sq feet Bajri + 1 sq feet Sand 530
7) Iron Girder (Used above Door) 500
8) Trolley of Mud 2000
TOTAL 59730
Subscribe to:
Posts (Atom)